Trinity – Cottonwood 115 kV Rebuild

Redding, CA

Project Overview


Line Reconductored

~2.5 Miles

Transmission Line

115 kV

Access Support

Helicopter

Completed

September 2024


Client

Pacific Gas and Electric Company

Location

Redding, CA

Services

Remote-Access 115 kV Transmission Rebuild & Reconductoring

The Trinity-Cottonwood project involved rebuilding portions of an existing 115 kV transmission line including replacement of inaccessible H-structure poles and reconductoring approximately 2.5 miles of line. Construction activities required the use of helicopters and specialized tracked equipment to access remote terrain while maintaining safe operations within an existing energized transmission corridor.

Full Scope of Work

Transmission Rebuild
  • Replacement of inaccessible H-structure poles.
  • Reconductoring of approximately 2.5 miles of existing 115 kV transmission line.
Remote Access
  • Helicopters used to support access to remote terrain.
  • Specialized tracked equipment used where conventional access was limited.
Energized Corridor Operations
  • Construction was performed within an existing energized transmission corridor with safety and coordination requirements.